Table 4: Costs associated with decommissioning of the Finlayson dam

Item Remarks Price (Year 2000 $C) Price (Year 2000 $US)
Mobilisation and demobilisation Lump sum $50,000 $33,385
Demolition About 400 m3 $80,000 $53,415
Fish habitat enhancement works Sweeper trees, log boulder clusters, root fans $23,000 $15,357
Shoreline stabilisation works Live stakes, seeding, bank stabilisation $11,100 $7345
Engineering, construction supervision and environmental assessments Design, tendering, civil/environmental site supervision $80,000 $53,415
Post construction environmental monitoring Site monitoring in 2001 and 2002 $10,000 $6667
TOTAL $254,100 $169,660