Table 4: Planned Lao hydro power export infrastructure

Source: Power System Development Plan August 2004

Tie-line Capacity (kV) Length (km) Status
Nam Theun 2-Roi Et, Thailand 500 190 construction
Nam Theun 2-Ha Tinh, C. Vietnam 500 130 technical assistance
Nam Mo-Ban Mai, N. Vietnam 230 ? planning
Nam Ngum-Udon Thani, Thailand 500 80 planning
Xe Kaman 3-Vietnam 230 ? planning
Xe Kong basin-Pleiku, S. Vietnam 500 120 planning