Projected schedule for refurbishing the third power plant

Activity Start Finish
Refurbish Units G22-24 April 2008 September 2017
Design March 2009 January 2010
Contracting January 2010 August 2011
Construction August 2011 September 2017
Plan and site prep August 2011 June 2013
Refurbish G-24 March 2013 September 2014
Refurbish G-23 September 2014 March 2016
Refurbish G-22 March 2016 September 2017
Refurbish Units G-19-21 To be determined
Refurbish exciters May 2007 October 2014
New governor controls September 2008 October 2014
Replace 236MVA transformers November 2006 November 2012
New 500kV cables February 2009 December 2011