2001, prior to commencing the Manapouri Half Life Refurbishment Project 2008, following completion of the Manapouri Half Life Refurbishment Project Improvement
Manapouri power station reliability 98.8% 99.2% 0.4%
Manapouri power station availability 82.4% 91.6% 9.2%