Hydro project in final stages

The Gerusoppa Sharavathi hydroelectric project in India has reached its final stages.

The 500 m long dam expected to be completed shortly across the Sharavathi river at Gerusoppa would enable water to be utilised for power generation.

The project will reuse the water flowing from Lingamakki and Jog Falls power houses. Power will be generated utilising four turbine units of 60 MW each.