Compelo is using cookies

We use them to give you the best experience. If you continue using our website, we'll assume that you are happy to receive all cookies on this website.

ContinueLearn More
Close

Bodangora Wind Farm, Wellington, New South Wales

  • Project Type

    Windfarm

  • Location

    Wellington, New South Wales, Australia

  • Capacity

    113.2MW

  • Annual Output

    361GWh

  • Estimated Investment

    A$237m ($180m)

  • Construction Started

    April 2017

  • Expected Completion

    Second half of 2018

  • Owner and Operator

    Infigen Energy

Bodangora windfarm is a 113.2MW onshore power project being developed approximately 20km north-east of Wellington town in central New South Wales (NSW), Australia. The project is estimated to cost more than A$237m ($180m).

The plant’s owner and operator Infigen Energy submitted a planning proposal for the wind project to the New South Wales (NSW) Department of Planning and Infrastructure in May 2012. The proposal was granted approval by the Planning Assessment Commission (PAC) in September 2013.

Construction on the windfarm began in April 2017, while operations are scheduled to commence in the second half of 2018. The first wind turbine was assembled at the facility in March 2018.

The project is expected to create approximately 120 jobs during the construction phase and seven full-time jobs during operation.

The Bodangora windfarm is expected to generate 361GWh of clean electricity a year, which will be sufficient to power 49,000 NSW households and offset more than 800,000t of carbon emissions a year.

It will also provide social, cultural and economic benefits to the local communities.

Bodangora windfarm location and infrastructure

The Bodangora windfarm is spread across 7,820ha of farmland, which is used for sheep and cattle grazing. The site lies in the South Western Slopes Bioregion between the foothills and isolated ranges.

It will be installed with 33 General Electric (GE) wind turbines rated at 3.43MW each. The maximum tip height of the turbine is 150m and the blade span diameter is 130m. The turbine’s blades are 63.7m in length and weigh approximately 19t.

The wind farm will feature an operation and maintenance building, a construction compound, parking, as well as temporary and permanent wind monitoring masts.

Approximately 39km of new and upgraded access tracks will be built at the site.

Financing

The Bodangora wind project is being financed through a combination of equity and debt.

The Clean Energy Finance Corporation (CEFC) and German Landesbank NORD/LB are providing debt facilities totalling A$163m ($124.3m), while Infigen is providing the remaining A$74m ($56.5m) in equity for the project.

Infigen will also contribute $50,000 a year to the Bodangora windfarm for 25 years from the start of operations.

Power transmission from Bodangora

Power generated by the Bodangora wind farm will be fed to a new 33/132kV substation and transmission line to be built at the facility. The transmission line will, in turn, connect the windfarm to the Transgrid 132kV network on the Wellington substation and Beryl transmission line.

“The Bodangora windfarm is expected to generate 361GWh of clean electricity a year.”

Other transmission infrastructure such as transformers, microwave towers, switchyards, and underground and overhead cabling will also be installed as part of the project.

Power purchase agreement

EnergyAustralia will purchase 60% of the renewable energy generated from the Bodangora windfarm. The sale will be made under a power purchase agreement (PPA) valid up to December 2030.

The remaining output will be sold by Infigen either to commercial and industrial customers or in spot/wholesale electricity market.

Contractors involved

A consortium comprising General Electric (GE) and Civil & Allied Technical Construction (CATCON) was awarded an engineering, procurement and construction (EPC) contract to build the Bodangora windfarm.

GE is responsible for the supply and installation of the wind turbines, while CATCON will oversee the construction activities.

Australian firm Consolidated Power Projects (CPP) was appointed as the primary contractor by TransGrid to construct the substation and transmission line.

NJ Construction was selected to perform construction and commissioning of access tracks and transmission line, under a subcontract with CPP.

Norton Rose Fulbright and Herbert Smith Freehills acted as the legal advisors to Infigen Energy for the development of the Bodangora windfarm.

Related whitepaper

Alphatec Work Report: Fluxys, LNG Gas Terminal